The last activity, activity C,
starts at the end of month number 2, and
only takes one month to finish.
What I said before, by using differentiating patterns or
colors, the bar chart or the Gantt chart can indicate monthly
progress toward physical completion of the construction
activities or the entire project in general.
So let's go through an example.
If we say that I'm going to shade in yellow
color that the work completed at end
of month 2, and I gave you this.
So the interpretation for this kind of example,
it tell us, let's go one by one,
construction activity A at the end of month 2,
40% of that activity been finished.
The question for you, what supposed to happen?
What's the planned for such a scheduling tool we have or
planning tool we have at end of month 2, activity A,
how long it's supposed to finish?